Most homes in Pound Ridge sit on two acres or more, so the well and the septic system can be far apart. Scotts Corners has small lots, and there the private wells and septic systems sit close together. The Town has said that layout, together with old pollutants and newer ones like PFAS, has made it "unsustainable" for businesses on Westchester Avenue to keep relying on their own wells.
On July 7, 2026, the Town Board voted unanimously to accept State Comptroller Thomas P. DiNapoli's final order, which created the Scotts Corners Water District. The district covers 39 commercially zoned parcels along Westchester Avenue, the same stretch where Pound Ridge buys groceries, eats dinner and runs most of its errands, as covered in our earlier look at the street.
The plan replaces the source of the water and almost nothing else. The Town designed the project so the business district stays the size it is today.
What was in the wells
The problem predates PFAS. The Katonah-Lewisboro Times reported in July that the legacy contaminants found in Scotts Corners well water include MTBE, a gasoline additive, along with PCE, a dry-cleaning solvent, and BTEX, a group of chemicals found in petroleum. The same report said the discovery of PFAS led the county Department of Health to issue notices of violation.
The Town has been working on Scotts Corners' water and septic problems for more than a decade. A Pound Ridge community profile published in 2022 records that a Wastewater Task Force was formed in 2015 to look for solutions to septic problems in the business district. At the July 7 meeting, according to the Mt. Kisco-Bedford Times, Ellen Ivens of the Water and Wastewater Task Force summarized PFAS testing from 30 sampling sites and said the findings "underscore the need to provide reliably clean drinking water to the area."
"This project is fundamentally about drinking water and public health," Town Supervisor Kevin Hansan said in the Town's July 10 announcement. "Scotts Corners has faced water quality challenges for many years."
The water will come from the golf club
The water source sits inside a property most residents know for another reason. The project will connect the district to an existing treated water storage tank at the Pound Ridge Golf Club on High Ridge Road. Aquarion Water Company owns and runs that tank. Aquarion will supply the district under an agreement with the Town that follows a Water Supply Agreement Term Sheet signed on March 4, 2026, and it will be responsible for water quality.
The supplier itself changed hands this summer. On July 1, 2026, the South Central Connecticut Regional Water Authority closed its $2.4 billion purchase of Aquarion from Eversource. Media reports describe Aquarion as now a quasi-public, standalone not-for-profit utility, as the Mt. Kisco-Bedford Times noted in its coverage of the July meeting.
Pound Ridge has been here before, as a neighbor. The Town describes the setup as "public water/private septic," a model already used in other northern Westchester communities, including Bedford and Lewisboro. At the same July meeting, Jill Faber of the Town's Economic Development Committee pointed out that other nearby towns without municipal water "wish they did."
What the district leaves alone
The terms of the project explain why Scotts Corners will look and feel much the same afterward.
No sewer. The project needs no new wastewater infrastructure. Water will come from a treated public supply, and every property will keep using its existing septic system. The Katonah-Lewisboro Times noted that some residents had feared new wastewater infrastructure, and the Town's statement says there won't be any.
Sized for today's use. In its own words, the Town says the project "is designed to serve existing needs" and "is not intended to support future development, only to provide clean drinking water at current usage levels." That language answers a concern raised during public discussion, that public water could lead to overdevelopment of Scotts Corners. The Town's first-year cost roster for the district, dated May 2024, shows what "current usage" means for dining. It lists restaurant uses at six Westchester Avenue addresses, with seat counts from 25 at No. 54 to 60 at No. 76, plus 40 at No. 69 and 50 each at Nos. 74 and 85.
Only the commercial strip. The district covers 39 commercially zoned parcels. Homes on Pound Ridge's large residential lots are outside it.
How the cost lines up
The Town's published maximum estimate for the project is $11.129 million. A $7.6 million grant under New York's Water Infrastructure Improvement Act covers 70% of eligible construction costs. In March 2026, the Town Board also authorized applications for congressional directed funding through Rep. Lawler and Sens. Schumer and Gillibrand, with the goal of lowering costs for district property owners. Engineering is the next large line item. The October 6, 2026 Town Board agenda included a request to approve Contract Addendum No. 4 with Laberge Group for the Scotts Corners Drinking Water Improvements project, with an estimated $1.8 million engineering fee and a $25,000 budget for reimbursable expenses.
Where the work stands this week
The district has been through a long series of approvals, and two steps remain before any digging starts.
| When | Step |
|---|---|
| 2015 | Wastewater Task Force formed to address Scotts Corners septic problems |
| Fall 2024 | District property owners and residents approve the water district, 20 to 15 |
| March 4, 2026 | Aquarion water supply term sheet signed |
| June 2026 | State Comptroller's Office authorizes the district |
| July 7, 2026 | Town Board accepts the final order, establishing the district |
| October 6, 2026 | Laberge Group engineering addendum on the Town Board agenda |
| November 4, 2026 | Request to assign Laberge's contracts to Artheon, Inc. on the Town Board agenda |
Before construction begins, the Town has to finalize the agreements that engineering and permitting depend on. Those will be discussed at public meetings of the Planning Board and the Town Board, neighboring property owners will be notified, and meeting dates will be posted on the Town's website calendar.
The Town calendar lists the next Town Board meetings for Tuesday, December 1, and Tuesday, December 15, both at 7:30 p.m. Project documents, including the PFAS sampling results and the cost roster, are on the Town's Scotts Corners Water District page.
When the work is finished, the 39 parcels on Westchester Avenue will draw water from Aquarion's tank at the Pound Ridge Golf Club, with the same septic systems in place and usage held to current levels.